Serfas Feedlot: 1.5 Million Cubic Meters of Dirt Moved!

Serfas Feedlot Design and Construction

When complete, the Serfas Feedlot will be able to accommodate 40,000 head of cattle! The project involved the excavation of 1.5 million cubic meters of earth and has spanned 240 acres. It includes the design and excavation of a 100-million-gallon storage pond that will supply the water needs for the feedlot.

Dennis Dirtworx was also responsible for road construction and all water mains for the cattle pens (17,000 lineal meters), and for implementing 32,000 square meters of Roller Compacted Concrete (RCC) upon project completion.  

Here are some of the progress photos of this project:

Share:

More Posts

Dennis Dirtworx logo white

Follow us on Facebook and Instagram!