This project relocated an open canal to a pipeline system. Dennis Dirtworx installed a large-diameter (1,050mm – 100mm) water main pipe, a total of 9,000 meters of pipeline, and 19 service risers to farmers.
Dennis Dirtworx also performed six Lethbridge County road crossings, with complete traffic management strategies applied. The team removed the existing infrastructure of concrete water management systems, and moved 80,000 cubic meters of earth in the process.
The original contract was extended to include another 1,100 meters of pipeline. A large concrete canal inlet structure was installed, complete with a gabion wall.