Chin 10 Canal Project
In this canal-cleaning project, Dennis Dirtworx performed two canal realignments. The project entailed a large-diameter culvert road crossing, multiple drop structures, and a 4,000-tonne armored bank lining. Overall, Dennis Dirtworx moved 30,000 cubic meters of earth to install five large concrete structures.
Nobleford Water Treatment Plant & Wastewater Lagoon
Dennis Dirtworx, an excavation company that serves all of southern Alberta, moved 70,000 cubic meters of earth to completely redesign existing lagoon structures. The project involved excavating a new facultative cell, de-sludging, and regrading existing facultative cells. All facultative cells received a 60-mil liner to prevent ground penetration. Three new anaerobic cells were constructed and […]
Fort Macleod Industrial Area Water & Sewer Renewal
Dennis Dirtworx is working on completely rehabilitating the existing 7,000-meter sanitary and water main in the Fort Macleod Industrial area. This project involves 45 services to existing residents, roads (gravel and asphalt), and landscaping restoration.
BRID Lomond Canal Rehab
This project involved 13 kilometers of canal cleaning and armoring. The original contract stipulated 7 km, but another 6 km were added post-contract. A total of 425,000 cubic meters of earth was moved. Moreover, 50,000 tonnes of armor was produced in-house, trucked, and placed along the canal. Dennis Dirtworx installed 30 structures ranging from farm […]
SMRID Cameron Project
Dennis Dirtworx relocated an open canal to a pipeline system. A large-diameter (1,200mm – 100mm) pipe water main was installed. Six Lethbridge County road crossings were performed, with complete traffic management strategies applied. Additionally, a 130-meter auger bore was coordinated and completed under the Canadian Pacific Railway and Highway. Three 9,100-meter pipelines were installed, and […]
SMRID 8-Mile Project
This project relocated an open canal to a pipeline system. Dennis Dirtworx installed a large-diameter (1,050mm – 100mm) water main pipe, a total of 9,000 meters of pipeline, and 19 service risers to farmers. Dennis Dirtworx also performed six Lethbridge County road crossings, with complete traffic management strategies applied. The team removed the existing infrastructure […]
Serfas Feedlot: 1.5 Million Cubic Meters of Dirt Moved!
When complete, the Serfas Feedlot will be able to accommodate 40,000 head of cattle! The project involved the excavation of 1.5 million cubic meters of earth and has spanned 240 acres. It includes the design and excavation of a 100-million-gallon storage pond that will supply the water needs for the feedlot. Dennis Dirtworx was also […]
Stafford Lake Project
This turnkey new subdivision earthworks project involved the excavation of 170,000 cubic meters of earth to construct a lakefront subdivision. A total of 3,325 lineal meters of potable and non-potable water mains were installed. The project also involved 20 lot service connections, subgrade preparation, 6,500 tonnes of granular materials, and 10,500 square meters of Type […]
NE Industrial, Coaldale
Dennis Dirtworx was involved in the second, third, and fourth phases of this turnkey subdivision project, which encompassed earthworks, underground utilities, and final asphalt surfacing. The team installed sanitary, stormwater, and potable water, along with 50 lot services. They moved 80,000 cubic meters of earth, undertook subgrade preparation, and completed 10,500 tons of granular material […]
Chin Canal Rehabilitation
Chin 2 involved the rehabilitation of a canal. 100,000 cubic meters of earth had to be moved to deconstruct the old infrastructure. A large-diameter (900mm – 100mm) Rip Rap water main was installed. The Dennis Dirtworx team was also responsible for multiple auger crossings under Alberta transportation highways, and for land restoration. The team worked […]